C5/K1/K3 Integrated Satellite Terminal System Installation
Rev. 0 3–9
1
2
3
4
5
6
7
8
9
10
TIGHTEN BOLTS PER ILLUSTRATED SEQUENCE
Figure 3-2. LNA Installation
3. Connect cables as follows:
a. Connect receive cable from the ODU to the IDU CP2 connector.
c.
Connect transmit cable from the ODU to the IDU CP1 connector.
d. Connect the receive cable to the C-Band LNA (mounted on the OMT).
e. Connect the transmit cable to the OMT.
4. Perform operational testing of the C-Band System as outlined in Chapter 6,
System Checkout.